With the infectious respiratory disease that originated in China and is known as Corona Virus (Covid-19) showing its effects worldwide in a short period of time and posing a global threat, the coronavirus was classified as a pandemic by the World Health Organization.
While the problems caused by the pandemic in the economic sphere, as in many other areas, increase day by day, delays or difficulties in performance are likely to occur, particularly in commercial relationships. In our country as well, the disruptions that will arise as a result of the precautionary measures implemented against the pandemic raise the question of whether the coronavirus pandemic can be characterized as force majeure in law.
What is Force Majeure?
In order to interpret whether the coronavirus constitutes force majeure, it is first necessary to define force majeure. Force majeure, although not explicitly defined in legislation, can generally be defined as an event that occurs without any fault, and that is impossible to foresee and prevent. Although force majeure is not defined in legislation, certain conditions are prescribed by both doctrine and Court of Cassation decisions for an event to be considered force majeure. Generally, these conditions are:- The event in question must have occurred without the fault of the parties
- It must be unforeseeable
- It must be impossible to prevent the event from rendering performance impossible despite all precautions
What Are the Consequences of Accepting the Coronavirus as Force Majeure?
If, upon evaluating all these matters together, the coronavirus is accepted as force majeure, the provisions regarding "impossibility of performance" regulated in Turkish Code of Obligations Article 136 shall apply. Accordingly:1- The obligation is extinguished!
Turkish Code of Obligations Article 136/1: "If the performance of an obligation becomes impossible due to reasons for which the debtor cannot be held responsible, the obligation is extinguished." Pursuant to this provision, if the fulfillment of obligations under the contract becomes impossible without the fault of the debtor, the debtor's obligation to fulfill their duties is eliminated.2- The debtor who is released from the obligation must return the performance received from the other party!
Even though the obligation is extinguished, pursuant to Article 136/2, the performance received under the contract whose performance has become impossible must be returned. Otherwise, a lawsuit may be filed under the provisions of unjust enrichment.3- The debtor is obligated to notify the creditor without delay that performance has become impossible and to take the necessary measures to prevent the increase of damages!
In the event of impossibility of performance, pursuant to Article 136/3, the debtor who learns that the performance of the obligation has become impossible due to force majeure must notify the creditor of this situation as soon as possible. Otherwise, the debtor will be liable to compensate the creditor's damages arising from such failure.4- If performance does not become impossible but becomes significantly more difficult, the relevant party may request adaptation!
In cases where performance has not become impossible due to force majeure but has become significantly more difficult, it is possible to request the adaptation of the contract to the new conditions pursuant to Turkish Code of Obligations Article 138, and in cases where adaptation is not possible, to exercise the right of rescission.What Are the Required Conditions for Requesting Adaptation?
- There must be an extraordinary situation that arose after the contract was concluded
- The party requesting adaptation must not have been able to foresee this extraordinary situation
- The obligation must not yet have been performed, or must have been performed with the rights arising from the excessive difficulty of performance reserved
- Expecting the debtor to perform must constitute a violation of the "good faith" principle under Turkish Civil Code Article 2